Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CGD PROJECT AT MADURAI, THENI AND VIRUDHNAGAR DISTRICTS.

Reported Date : 11-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    9

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
132801328

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
73.0872.453.68149.21

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/203012/203012/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
90.560

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

"Cumulative Achievement: CNG (No.) - 18 Steel (Inch Km) - 402 D - PNG (No.)- 1681 Extension received from PNGRB due to non - availability of pipeline connectivity in the vicinity of the GA."

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone