Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : SETTING UP OF NEW RAIL FED POL FACILITY AT KAMARDANGA, ASSAM.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 52 / 31 / 21

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
384.040384.04

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
81.216.616.1894

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20277/20277/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
87.460

Ministry Review Date

LatestLastPhysical Progress (%)Status
34.4Ongoing

Monthly Status

Background Information

• Land development works Completed. • Compound wall- 74.66% physical progress achieved. RCC of Footing: 2800/3000 RMT Completed. RCC in Retaining Wall - 2600/3000 RMT Completed. RCC in superstructure completed - 2200/3000 RMT Completed. Masonry work completed - 2200/3000 RMT Boundary wall length completed. • Building works- 55.63% Physical progress achieved. TT Amenity Building – WIP for roof slab, 100% column lift completed. Marketing Room Gate Cabin - Plastering in progress. Automation Control Room - Plastering in progress. Admin Building -2nd floor roof slab completed. Brick work in progress. MCC Room: 90 % Trench works completed. WIP for roof slab. Engineering Store Room -Grade slab in progress. IBAC Room – Plastering in progress. • TT Parking Driveway jobs-Completed • Tankage Works - 74.08% physical progress achieved towards MS tanks and UG tanks. 79.36% physical progress achieved towards HSD/SKO/ATF tanks. • Structural Shed jobs- 71.48% physical progress achieved in structural sheds. 1. TLF PH: Pump foundations in progress. Structure erection in progress. 2. FW PH: All pump foundations completed. 3. Air Compressor Shed: Civil works completed. Structure works in progress. 4. Calibration Shed: Foundation completed. Flooring and structure erection in progress. 5. TT Gantry – Plinth beam casting in progress.Partial PEB structure received. • Piping Jobs- 42.53% physical progress achieved. 1) RCC pedestal for Fire water and product pipelines in p around TT Gantry and tank dyke area completed 2) 95% TWD pipelines at railway siding completed 3) Railway siding drain RCC – 300m/650m completed. 4) TWD manifold civil works completed. TLF manifold civil works in progress. 5) Trestle bridge, Piping works in progress in around TT Gantry and Dyke farms. • P way and earth filling jobs at Railway siding- Purchase orders for both the works are placed.15% physical progress achieved for earth work formation. P-Way works in progress inside depot premises. However, the works are on hold due to pending ESP approval from Railways. -PO placed for Car Hiring services & QRA/HAZOP/ERDMP study services. -PO placed for temporary fencing and Railway IPA. -PO placed for Construction of compound wall. -Placement of POs for Land development works and -TT parking area development works in progress . -TE/CE for Supply of product pipes, Steel plates. -Supply of ROSOV/TOBV tender sent to purchase for refloating. -PR for Supply of Fire Water Pipes and Supply of High Mast submitted to purchase for floating tender.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   </