• Land development works Completed.
• Compound wall- 74.66% physical progress achieved. RCC of Footing: 2800/3000 RMT Completed. RCC in Retaining Wall - 2600/3000 RMT Completed. RCC in superstructure completed - 2200/3000 RMT Completed. Masonry work completed - 2200/3000 RMT Boundary wall length completed.
• Building works- 55.63% Physical progress achieved. TT Amenity Building – WIP for roof slab, 100% column lift completed. Marketing Room Gate Cabin - Plastering in progress. Automation Control Room - Plastering in progress. Admin Building -2nd floor roof slab completed. Brick work in progress. MCC Room: 90 % Trench works completed. WIP for roof slab. Engineering Store Room -Grade slab in progress. IBAC Room – Plastering in progress.
• TT Parking Driveway jobs-Completed
• Tankage Works - 74.08% physical progress achieved towards MS tanks and UG tanks. 79.36% physical progress achieved towards HSD/SKO/ATF tanks.
• Structural Shed jobs- 71.48% physical progress achieved in structural sheds. 1. TLF PH: Pump foundations in progress. Structure erection in progress. 2. FW PH: All pump foundations completed. 3. Air Compressor Shed: Civil works completed. Structure works in progress. 4. Calibration Shed: Foundation completed. Flooring and structure erection in progress. 5. TT Gantry – Plinth beam casting in progress.Partial PEB structure received.
• Piping Jobs- 42.53% physical progress achieved. 1) RCC pedestal for Fire water and product pipelines in p around TT Gantry and tank dyke area completed 2) 95% TWD pipelines at railway siding completed 3) Railway siding drain RCC – 300m/650m completed. 4) TWD manifold civil works completed. TLF manifold civil works in progress. 5) Trestle bridge, Piping works in progress in around TT Gantry and Dyke farms.
• P way and earth filling jobs at Railway siding- Purchase orders for both the works are placed.15% physical progress achieved for earth work formation. P-Way works in progress inside depot premises. However, the works are on hold due to pending ESP approval from Railways.
| -PO placed for Car Hiring services & QRA/HAZOP/ERDMP study services.
-PO placed for temporary fencing and Railway IPA.
-PO placed for Construction of compound wall.
-Placement of POs for Land development works and -TT parking area development works in progress .
-TE/CE for Supply of product pipes, Steel plates.
-Supply of ROSOV/TOBV tender sent to purchase for refloating.
-PR for Supply of Fire Water Pipes and Supply of High Mast submitted to purchase for floating tender.
|