Steel plates, product pipes, fittings, strainers, hydrant pipes, high masts, light fittings, fire water pumps,
ROSOVs, FW Pumps, Jockey pumps, HVLRs received at site.
l.Compound wall- 81.36% physical progress achieved 2.Building works- 61.04% Physical progress achieved 3.Tankage Works - 76% physical progress achieved. 4.Piping Jobs- 49.21% physical progress achieved. 5.31% physical progress acheived for RCC Roads and associated drains 6.13.3% physical progress acheived for Flexible pavement and associated drains. P way and earth filling jobs at Railway siding- Purchase orders for both the works are placed.20.35% physical
progress achieved for earth work formation. P-Way works 3.3% progress acheived inside depot premises.
However, works at ouside premises are on hold due to pending ESP approval from Railways.
Supply of TWD Product Pumps, UG Pumps, MOVs, transformer, DG set, cables, panels and TLF pumps -
Document Approval completed, manufacturing is in progress. | -PO placed for Car Hiring services & QRA/HAZOP/ERDMP study services.
-PO placed for temporary fencing and Railway IPA.
-PO placed for Construction of compound wall.
-Placement of POs for Land development works and -TT parking area development works in progress .
-TE/CE for Supply of product pipes, Steel plates.
-Supply of ROSOV/TOBV tender sent to purchase for refloating.
-PR for Supply of Fire Water Pipes and Supply of High Mast submitted to purchase for floating tender.
|