Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : GRASS ROOT RAIL FED DEPOT AT SEKERKOTE, AGARTALA AS RESITEMENT OF EXISTING DHARMANAGAR DEPOT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    1

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6560656

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
383.5111.6720.68415.86

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20259/20259/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
900

Ministry Review Date

LatestLastPhysical Progress (%)Status
82.2Ongoing

Monthly Status

Background Information

1) Civil Works • Non-Plant Buildings:(PMCC, Control Room, Admin & Amenity Block, Invoice Room, Security Room, M& R Room, etc.): Completed • Boundary Wall: Land development & compound wall incl. retaining wall: Completed • Plant Buildings: Fire Water Pump House(P/H), TLF P/H, TWD P/H, TLF Gantry, Pipe Bridge, Cable Tree & Bridges: Completed • Road & Drain Works: WIP (29.50%) Initial contract terminated. Re-tender done in Apr’24 & LOA issued in Jul’24. Site handed over in Aug’24, Work in Progress. 2) Mechanical works • Tankage: Fire Water Tanks (2 nos.), HSD (2 nos.), MS (3 nos.) and SKO (2 nos.), UG Tanks (3 nos.) Completed • Pipelines: WIP (91.35%) o TLF, TWD, Tank & FW PH Manifold laying complete. WIP - OWS Pit, Hydrotesting, Radiography, Painting, Product & FH P/L Work for Tank Wagon Decantation Gantry. 3) Electrical Works (74.90%) o DED Completed. Cable tray, High masts, Earthing Strips, Transformers, DG, Cables, FLP Fittings, DBs delivered. Installation under progress. 4) Automation works. (47.50%) o DED Completed. Procurement under progress & material/equipment being delivered progressively. 5) VRU works. (40.00%) o DED Completed. Procurement & Fabrication WIP. Boundary Wall Package (99.4%), Non-Plant Building (100%), Tankage (81%), Plant Building (73%) and Pipeline works (21%). Work in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone