1) Civil Works
• Non-Plant Buildings:(PMCC, Control Room, Admin & Amenity Block, Invoice Room, Security Room, M& R Room, etc.): Completed
• Boundary Wall: Land development & compound wall incl. retaining wall: Completed
• Plant Buildings: Fire Water Pump House(P/H), TLF P/H, TWD P/H, TLF Gantry, Pipe Bridge, Cable Tree & Bridges: Completed
• Road & Drain Works: WIP (31%) Initial contract terminated. Re-tender done in Apr’24 & LOA issued in Jul’24. Site handed over in Aug’24, Work in Progress. Work part-offloaded in Jun’25 due to poor performance.
2) Mechanical works
• Tankage: Fire Water Tanks (2 nos.), HSD (2 nos.), MS (3 nos.) and SKO (2 nos.), UG Tanks (3 nos.) Completed
• Pipelines: WIP (92.8%)
o TLF, TWD, Tank & FW PH Manifold laying complete. WIP - OWS Pit, Hydrotesting, Radiography, Painting, Product & FH P/L Work for Tank Wagon Decantation Gantry.
3) Electrical Works (75.7%)
o DED Completed. Cable tray, High masts, Earthing Strips, Transformers, DG, Cables, FLP Fittings, DBs delivered. Installation under progress.
4) Automation works. (51%)
o DED Completed. DCS, Safety PLC, Cables, Cable Trays, TFMS delivered. Installation under progress.
5) VRU works. (43.5%)
o DED Completed. Procurement & Fabrication WIP
| Boundary Wall Package (99.4%), Non-Plant Building (100%), Tankage (81%), Plant Building (73%) and Pipeline works (21%). Work in progress. |