1) Civil Works
• Non-Plant Buildings:(PMCC, Control Room, Admin & Amenity Block, Invoice Room, Security Room, M& R Room, etc.): Completed
• Boundary Wall: Land development & compound wall incl. retaining wall: Completed
• Plant Buildings: Fire Water Pump House(P/H), TLF P/H, TWD P/H, TLF Gantry, Pipe Bridge, Cable Tree & Bridges: Completed
• Road & Drain Works: WIP (29.50%) Initial contract terminated. Re-tender done in Apr’24 & LOA issued in Jul’24. Site handed over in Aug’24, Work in Progress.
2) Mechanical works
• Tankage: Fire Water Tanks (2 nos.), HSD (2 nos.), MS (3 nos.) and SKO (2 nos.), UG Tanks (3 nos.) Completed
• Pipelines: WIP (91.35%)
o TLF, TWD, Tank & FW PH Manifold laying complete. WIP - OWS Pit, Hydrotesting, Radiography, Painting, Product & FH P/L Work for Tank Wagon Decantation Gantry.
3) Electrical Works (74.90%)
o DED Completed. Cable tray, High masts, Earthing Strips, Transformers, DG, Cables, FLP Fittings, DBs delivered. Installation under progress.
4) Automation works. (47.50%)
o DED Completed. Procurement under progress & material/equipment being delivered progressively.
5) VRU works. (40.00%)
o DED Completed. Procurement & Fabrication WIP.
| Boundary Wall Package (99.4%), Non-Plant Building (100%), Tankage (81%), Plant Building (73%) and Pipeline works (21%). Work in progress. |