Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : CGD PROJECT IN TONK, SAWAI MADHOPUR, DAUSA, KARAULI.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 45 / 44 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
175101751

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
281.3411.473.35296.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20300/03/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1260

Ministry Review Date

LatestLastPhysical Progress (%)Status
24.7Ongoing

Monthly Status

Background Information

82 in-KM of steel pipeline laid during the month. Steel Pipeline routes finalized and revised simulation completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone