Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : CGD PROJECT IN BIHAR JHARKHAND.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 45 / 44 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
137701377

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
238.5539.265.07282.88

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20300/06/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1550

Ministry Review Date

LatestLastPhysical Progress (%)Status
24.15Ongoing

Monthly Status

Background Information

Survey works: ¿ 270 Km out of 450 Km approx. Reconnaissance Survey completed by M/S AMIN. ¿ 173 Km out of 300 Km Detailed Route Survey completed. ¿ 43.115 Sq. Km out of 150 Sq. Km Area Survey of MDPE Network completed ¿ Route survey in all aspect completed from GAIL SV 31 Gangpur West Bengal to Dumka Jharkhand ¿ Detail route survey has been completed from Dumka to Sahibganj 38 KM. ¿ Detail route survey has been completed from Dumka to Banka 96 KM. Steel Laying: • Steel Laying for this Month – 23.60 (Inch-KM) • Cumulative steel laying – 1171.37 Inch-Km CNG Status: • CNG Station Commissioned this month – 0 Nos • Cumulative CNG station commissioned till this month – 19 (Nos) MDPE Laying: • MDPE pipeline Laid in this month – 7 km • Cumulative MDPE pipeline Laid till this month – 70.24 KM 40 in-KM of steel line laid during the month. Civil works in progress at 12 CNG stations.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

 &nb