Survey Work
• 281.924 km of reconnaissance survey completed by M/s AIMN.
• 295.922 km of DES (Topography) completed by M/s AIMN.
Steel Laying:
• Steel Laying for Month – 88.72 (Inch-KM)
• Cumulative steel laying – 1231.05 Inch-Km
CGS Work
• M/S Nops Infrastructure has been awarded for Construction of CGS at Panagarh.
• Layout marking has been done. Civil, Mechanical and electrical Work in progress.
• Electricity connection: Joint visit has been completed on 23.01.2025.Payment done on 13.06.2025.
MS Work
• M/s AMP Infra Pvt. Ltd has been awarded for Construction of MS at Illambazar.
• Land demarcation has been completed on 04.03.2025.
• Bhumi pujan has been completed 06.03.2025.
• Topographical survey has completed on 06.03.2025.
• Layout marking has been done. B/w- PCC work in progress.
CNG Status:
• CNG Station Commissioned this month – 00 Nos
• Cumulative CNG station commissioned till this month – 16 (Nos)
LMC:
• LMC Done in this month- 285 Nos
• Cumulative LMC Done till this month- 2983 Nos
MDPE Laying:
• MDPE pipeline Laid in this month – 4.93 km
• Cumulative MDPE pipeline Laid till this month – 62.77 Km
| 273.5 km out 360km of reconnaissance survey completed. 213.11 km out of 240 Km DES Topography completed.
76 in-KM steel pipe laid during the month. |