Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : CGD PROJECT IN WEST BENGAL 11TH ROUND.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 45 / 44 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
262802628

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
219.1691.859.82320.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20300/06/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1710

Ministry Review Date

LatestLastPhysical Progress (%)Status
24.1Ongoing

Monthly Status

Background Information

Survey Work • 281.924 km of reconnaissance survey completed by M/s AIMN. • 295.922 km of DES (Topography) completed by M/s AIMN. Steel Laying: • Steel Laying for Month – 88.72 (Inch-KM) • Cumulative steel laying – 1231.05 Inch-Km CGS Work • M/S Nops Infrastructure has been awarded for Construction of CGS at Panagarh. • Layout marking has been done. Civil, Mechanical and electrical Work in progress. • Electricity connection: Joint visit has been completed on 23.01.2025.Payment done on 13.06.2025. MS Work • M/s AMP Infra Pvt. Ltd has been awarded for Construction of MS at Illambazar. • Land demarcation has been completed on 04.03.2025. • Bhumi pujan has been completed 06.03.2025. • Topographical survey has completed on 06.03.2025. • Layout marking has been done. B/w- PCC work in progress. CNG Status: • CNG Station Commissioned this month – 00 Nos • Cumulative CNG station commissioned till this month – 16 (Nos) LMC: • LMC Done in this month- 285 Nos • Cumulative LMC Done till this month- 2983 Nos MDPE Laying: • MDPE pipeline Laid in this month – 4.93 km • Cumulative MDPE pipeline Laid till this month – 62.77 Km 273.5 km out 360km of reconnaissance survey completed. 213.11 km out of 240 Km DES Topography completed. 76 in-KM steel pipe laid during the month.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks