Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : SETTING UP OF 10 MW ELECTROLYSER FOR PRODUCING GREEN HYDROGEN.

Reported Date : 05-JUN-24

Monthly Report : 5 / 2024

  

   

Total/Pending/Completed Milestone - 7 / 1 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2310211

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
103.52.10105.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20230/06/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1313

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks