Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : ANDHERI RESIDENTIAL TOWERS MUMBAI.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   38.5

Time Overrun (Months)-    13

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
281.35389.67389.67

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
214.142.740216.88

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20256/20266/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
800

Ministry Review Date

LatestLastPhysical Progress (%)Status
50.5Ongoing

Monthly Status

Background Information

> Old residential buildings Q & R Demolished. > Tree cutting (30 Nos) and Transplantation (146 Nos) completed. > Shore Pile 422/422 completed. > Shore pile capping beam work 322m/322m. > Inclined Anchoring : 150/150 NOs > Passive Anchoring completed (1480 Nos). > Mass excavation (soil & Rock) for basement work Completed (60000m3). > PCC below foundation completed. > Water proofing (below foundation level) : completed > Raft & foundation for Building 1 & 2 completed. > B1- Stilt + 4rd floor casting completed and WIP for 5th Floor Slab. Block work completed for 1st floor. > B2- Stilt + 8th floor casting completed and WIP for 9th Floor Slab. Block work completed for 3rd floor. > Non Tower Area : 99% of NTA (upper basement casting completed), WIP for STP in basement 1 and Ramp Work.> Construction commenced from 15.05.2023. > Demolition of old building completed. > Tree cutting completed and Transplantion of trees completed. > Shore piling works completed. > Shore pile capping beam works completed. > Inclined Anchoring completed: 1020/1480 Nos > Mass excavation (soil & Rock) for basement work completed > PCC below foundation 866/938.85 m3 , WIP > Water proofing (below foundation level) : 421.9/938.85 m2 > Raft and foundation for building 2 is in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone