> Old residential buildings Q & R Demolished.
> Tree cutting (30 Nos) and Transplantation (146 Nos) completed.
> Shore Pile 422/422 completed.
> Shore pile capping beam work 322m/322m.
> Inclined Anchoring : 150/150 NOs
> Passive Anchoring completed (1480 Nos).
> Mass excavation (soil & Rock) for basement work Completed (60000m3).
> PCC below foundation completed.
> Water proofing (below foundation level) : completed
> Raft & foundation for Building 1 & 2 completed.
> B1- Stilt + 4rd floor casting completed and WIP for 5th Floor Slab. Block work completed for 1st floor.
> B2- Stilt + 8th floor casting completed and WIP for 9th Floor Slab. Block work completed for 3rd floor.
> Non Tower Area : 99% of NTA (upper basement casting completed), WIP for STP in basement 1 and Ramp Work. | > Construction commenced from 15.05.2023.
> Demolition of old building completed.
> Tree cutting completed and Transplantion of trees completed.
> Shore piling works completed.
> Shore pile capping beam works completed.
> Inclined Anchoring completed: 1020/1480 Nos
> Mass excavation (soil & Rock) for basement work completed
> PCC below foundation 866/938.85 m3 , WIP
> Water proofing (below foundation level) : 421.9/938.85 m2
> Raft and foundation for building 2 is in progress |