Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
20
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
LOA placed for Tankage Works. Work yet to commence. Confirmatory Soil Investigation completed and in view of huge difference in Soil Investigation Reports, fresh Soil Investigation carried out through EPCM Consultant. Reports received and design & BoQ preparation in progress.
Work Order placed for Civil Works on 24.01.2025. Fire Screen work completed and Excavation work for customer care building is in progress. WIP (0.5%)
LOA placed for pipelines works on 03.06.2025. | LOA placed for Tankage Works. Work yet to commence.
Tender for civil and pipelines works under invitation |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |