Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : AUGMENTATION OF FACILITIES AT MATHURA BITUMEN PLANT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
260.120260.12

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1.030.041.07

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/202512/202612/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100

Ministry Review Date

LatestLastPhysical Progress (%)Status
25Ongoing

Monthly Status

Background Information

LOA placed for Tankage Works. Work yet to commence. Confirmatory Soil Investigation completed and in view of huge difference in Soil Investigation Reports, fresh Soil Investigation carried out through EPCM Consultant. Reports received and design & BoQ preparation in progress. Work Order placed for Civil Works on 24.01.2025. WIP : Fire Screen work completed, site clearance for Store Room and Customer Care Building completed. Customer Care Buildings: Excavation work for customer care building completed, sand filling upto PCC level completed, PCC below foundation completed. TMT Bar cutting and binding is in progress.Store room: Excavation completed but due to high water level at site, sand filling could not completed. Well point dewatering system is being provided for lowering water level so that work can be completed.Control Room: The pile foundation drawings received. The machines for piling works has been finalised. Test piles will be constructed at site.Design Mix Materials report received. LOA placed for pipelines works on 03.06.2025.LOA placed for Tankage Works. Work yet to commence. Tender for civil and pipelines works under invitation

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks