1) Civil Works- I (Land Development Boundary Wall): - 1st tender cancelled
• LOA placed on 22/07/24 Work in Progress.
• Work in Progress – 20.59 %
2) Civil Works- II (Non-Plant Buildings): -
• Site handed over to contractor on 20/12/23.
• Work in Progress – 49.12%
• Building work in Progress
3) Mechanical works (Tankage): -
• Site handed over to contractor on 05/01/24.
• Work in Progress – 49.69 %.
• Tank fabrication works in progress.
4) Mechanical works (Pipeline): -
• Site handed over to contractor on 20/02/24.
• Work in Progress – 44.10 %.
• Construction of pipe pedestal, area grading, procurement of pipe fittings in progress.
• Pipeline Fabrication works in Progress
5) Electrical Work : -
• Work order Placed on 29.03.2025.
• Work in Progress : 6.0 %.
• Detailed engineering and Material Procurement in Progress.
| Site handed over to Civil Package 2 Contractor (Non Plant Building) - Footing excavation works in progress. WIP 2%
Site handed over to Mechanical Package 1 Contractor (Tankage Works). Footing excavation works in progress. WIP 3.22%
Site handed over to Mechanical Package 2 (Pipeline) Vendor on 20/02/24. WIP 0.3% |