1) Civil Works- I (Non-Plant Buildings): -
• Contract foreclosed due to delay in receipt of Statutory approval and due to major change in scope. Re tender done. LOA placed on 22/07/24 Work in Progress.
• Work in Progress – 20.09 %
2) Civil Works- II (Non-Plant Buildings): -
• Site handed over to contractor on 20/12/23.
• Work in Progress – 46.81%
• Building work in Progress
3) Mechanical works (Tankage): -
• Site handed over to contractor on 05/01/24.
• Work in Progress – 48.50 %.
• Tank foundation & Tank fabrication works in progress.
4) Mechanical works (Pipeline): -
• Site handed over to contractor on 20/02/24.
• Work in Progress – 41.23 %.
• Construction of pipe pedestal, area grading, procurement of pipe fittings in progress.
Pipeline Fabrication works in Progress
| Site handed over to Civil Package 2 Contractor (Non Plant Building) - Footing excavation works in progress. WIP 2%
Site handed over to Mechanical Package 1 Contractor (Tankage Works). Footing excavation works in progress. WIP 3.22%
Site handed over to Mechanical Package 2 (Pipeline) Vendor on 20/02/24. WIP 0.3% |