Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : GRASS-ROOT TERMINAL AT MIRZAPUR UTTAR PRADESH.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
980.450980.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
177.0723.486.3206.85

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20260/011/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1209.06

Ministry Review Date

LatestLastPhysical Progress (%)Status
50.75Ongoing

Monthly Status

Background Information

1) Civil Works- I (Land Development Boundary Wall): - 1st tender cancelled • LOA placed on 22/07/24 Work in Progress. • Work in Progress – 20.59 % 2) Civil Works- II (Non-Plant Buildings): - • Site handed over to contractor on 20/12/23. • Work in Progress – 49.12% • Building work in Progress 3) Mechanical works (Tankage): - • Site handed over to contractor on 05/01/24. • Work in Progress – 49.69 %. • Tank fabrication works in progress. 4) Mechanical works (Pipeline): - • Site handed over to contractor on 20/02/24. • Work in Progress – 44.10 %. • Construction of pipe pedestal, area grading, procurement of pipe fittings in progress. • Pipeline Fabrication works in Progress 5) Electrical Work : - • Work order Placed on 29.03.2025. • Work in Progress : 6.0 %. • Detailed engineering and Material Procurement in Progress. Site handed over to Civil Package 2 Contractor (Non Plant Building) - Footing excavation works in progress. WIP 2% Site handed over to Mechanical Package 1 Contractor (Tankage Works). Footing excavation works in progress. WIP 3.22% Site handed over to Mechanical Package 2 (Pipeline) Vendor on 20/02/24. WIP 0.3%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

&