Major foundation works completed and underground pipe laying in progress.Composite works: Sub-ordering of major items completed. Structural fabrication in progress, 707 out of 752 MT
completed. Piping fabrication is in progress, 29124 ID out of 49237 ID completed. Physical progress achieved was 78.2% against a planned progress of 94.6%. | Job for Civil & structural work awarded on 15.02.24.
2. Job for Composite works awarded on 08.03.24.
l Construction :
Civil works commenced on 15.03.24.
|