Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : INSTALLATION OF INDEPENDENT DE- AROMATIZED SOLVENTS PRODUCTION FACILITIES AT MUMBAI REFINERY.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4050405

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
170.034.096.88181

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20250/07/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
350

Ministry Review Date

LatestLastPhysical Progress (%)Status
78.2Ongoing

Monthly Status

Background Information

Major foundation works completed and underground pipe laying in progress.Composite works: Sub-ordering of major items completed. Structural fabrication in progress, 707 out of 752 MT completed. Piping fabrication is in progress, 29124 ID out of 49237 ID completed. Physical progress achieved was 78.2% against a planned progress of 94.6%.Job for Civil & structural work awarded on 15.02.24. 2. Job for Composite works awarded on 08.03.24. l Construction : Civil works commenced on 15.03.24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone