Major foundation works completed and underground pipe laying in progress.Composite works: Sub-ordering of major items completed. Structural fabrication in progress, 731 out of 752 MT
completed. Piping fabrication is in progress, 35732 ID out of 49237 ID completed. Physical Progress achieved was 81.5% against a planned progress of 98.7%. | Job for Civil & structural work awarded on 15.02.24.
2. Job for Composite works awarded on 08.03.24.
l Construction :
Civil works commenced on 15.03.24.
|