Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : INSTALLATION OF INDEPENDENT DE- AROMATIZED SOLVENTS PRODUCTION FACILITIES AT MUMBAI REFINERY.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4050405

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
170.0310.978.8189.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20250/07/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
350

Ministry Review Date

LatestLastPhysical Progress (%)Status
81.5Ongoing

Monthly Status

Background Information

Major foundation works completed and underground pipe laying in progress.Composite works: Sub-ordering of major items completed. Structural fabrication in progress, 731 out of 752 MT completed. Piping fabrication is in progress, 35732 ID out of 49237 ID completed. Physical Progress achieved was 81.5% against a planned progress of 98.7%.Job for Civil & structural work awarded on 15.02.24. 2. Job for Composite works awarded on 08.03.24. l Construction : Civil works commenced on 15.03.24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks