1)OSBL construction activities started. Achieved 74.3% progress.9.4 km pipe laying completed for both 12 ATF & 20 HSD lines. HDD of 24 Pipeline successfully completed on 8th August 2024 from NJRP to Sandbank island(Approx 1 KM).City works HDD at DH road, MG road & Chittoor road crossings completed.
2)Composite works package-2 (ISBL)-Survey work inside refinery completed: Achieved 65.3% progress. Piping works in progress Civil works in progress Tank modification works, painting, primary & secondary seal installation & Hydrotest completed for YT310&YT330 tanks. Dome roof installation and leak test completed. E&I jobs are in progress.
| Composite Work package-1 (OSBL) job awarded on 08.03.2024. |