Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : REPLACEMENT AND EXTENSION OF JETTY PIPELINES AT KOCHI REFINERY.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
621.870621.87

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
153.9212.681.9168.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20260/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
120

Ministry Review Date

LatestLastPhysical Progress (%)Status
81.5Ongoing

Monthly Status

Background Information

1)OSBL construction activities started. Achieved 74.3% progress.9.4 km pipe laying completed for both 12 ATF & 20 HSD lines. HDD of 24 Pipeline successfully completed on 8th August 2024 from NJRP to Sandbank island(Approx 1 KM).City works HDD at DH road, MG road & Chittoor road crossings completed. 2)Composite works package-2 (ISBL)-Survey work inside refinery completed: Achieved 65.3% progress. Piping works in progress Civil works in progress Tank modification works, painting, primary & secondary seal installation & Hydrotest completed for YT310&YT330 tanks. Dome roof installation and leak test completed. E&I jobs are in progress. Composite Work package-1 (OSBL) job awarded on 08.03.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone