Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : REPLACEMENT AND EXTENSION OF JETTY PIPELINES AT KOCHI REFINERY.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
621.870621.87

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
153.9214.5811.59180.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20260/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
120

Ministry Review Date

LatestLastPhysical Progress (%)Status
82.5Ongoing

Monthly Status

Background Information

1)OSBL construction activities started. Achieved 75.6% progress.9.4 km pipe laying completed for both 12 ATF & 20HSD lines. HDD of 24 Pipeline successfully completed on 8th August 2024 from NJRP to Sandbank is land(Approx 1 KM).City works HDD at DH road, MG road & Chittoor road crossings completed. 2)Composite works package-2 (ISBL)-Survey work inside refinery completed: Achieved 67.2% progress. Piping works in progress Civil works in progress Tank modification works, painting, primary & secondary seal installation & Hydrotest completed for YT310&YT330 tanks. Dome roof installation and leak test completed. E&I jobs are in progress.Composite Work package-1 (OSBL) job awarded on 08.03.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks