Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : MANGALORE REFINERY AND PETROCHEMICALS LIMITED.
Project Name : POWER SYSTEM UPGRADATION PROJECT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 5 / 1 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3850385

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
119.42.737.59129.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20260/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
224.530

Ministry Review Date

LatestLastPhysical Progress (%)Status
59.7Ongoing

Monthly Status

Background Information

KPTCL cost estimation/SOR received on 16.06.2025. 1.For Aromatics, original LSTK contract was terminated due to non performance on 24.09.2024. The contractor went to court and finally Honourable HC-Bengaluru has given favourable verdict to MRPL on 17/02/2025. No jobs/ actions could be taken from 24.09.2024 till 17.02.2025. After the favourable verdict, MRPL took actions directly for procurement activity & completed the order placement for all the items required for Aromatic complex. MRPL placed orders for civil & electrical works for Aromatic complex and all erection activities completed. CEA application filed for approval. Expected completion by 15.07.2025. 2.All works other than Main Receiving Station (MRS) package works shall be completed by November-2025.Ordering: Refinery complex- Main EPC package for 220kV SS – price bid opened. Pipe Fittings – price bid opened. Motorised Butterfly valves – under evaluation. Motorised Globe Valves – under evaluation. Manual Butterfly valves & NRVs– price bid opened. Flanges – price bid opened. Pipes – evaluation under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks