Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : MANGALORE REFINERY AND PETROCHEMICALS LIMITED.
Project Name : POWER SYSTEM UPGRADATION PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 1 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3850385

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
119.42.47.26122.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20260/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
224.530

Ministry Review Date

LatestLastPhysical Progress (%)Status
56.88Ongoing

Monthly Status

Background Information

a)For Aromatics, original LSTK contract was terminated due to non performance on 24.09.2024. The contractor went to court and finally Honourable HC-Bengaluru has given favourable verdict to MRPL on 17/02/2025. No jobs/ actions could be taken from 24.09.2024 till 17.02.2025. After the favourable verdict, MRPL took actions directly for procurement activity & completed the order placement for all the items required for Aromatic complex. MRPL placed orders for civil & electrical works for Aromatic complex and are under progress at site. b) From Bajpe Receiving station the power infrastructure is being executed by MRPL under KPTCL supervision. For this work, KPTCL estimation along with specification for works to be executed by MRPL to draw Power at 220kV level from Main Receiving Station (MRS), Bajpe is required. The MRPL project completion will be delayed in case approval is not received at the earliest. - Continuous follow up being carried out with M/s KPTCL. Ordering: Refinery complex- Main EPC package for 220kV SS – price bid opened. Pipe Fittings – price bid opened. Motorised Butterfly valves – under evaluation. Motorised Globe Valves – under evaluation. Manual Butterfly valves & NRVs– price bid opened. Flanges – price bid opened. Pipes – evaluation under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone