a)For Aromatics, original LSTK contract was terminated due to non performance on 24.09.2024. The contractor went to court and finally Honourable HC-Bengaluru has given favourable verdict to MRPL on 17/02/2025. No jobs/ actions could be taken from 24.09.2024 till 17.02.2025. After the favourable verdict, MRPL took actions directly for procurement activity & completed the order placement for all the items required for Aromatic complex. MRPL placed orders for civil & electrical works for Aromatic complex and are under progress at site.
b) From Bajpe Receiving station the power infrastructure is being executed by MRPL under KPTCL supervision. For this work, KPTCL estimation along with specification for works to be executed by MRPL to draw Power at 220kV level from Main Receiving Station (MRS), Bajpe is required. The MRPL project completion will be delayed in case approval is not received at the earliest.
- Continuous follow up being carried out with M/s KPTCL.
| Ordering:
Refinery complex-
Main EPC package for 220kV SS – price bid opened.
Pipe Fittings – price bid opened.
Motorised Butterfly valves – under evaluation.
Motorised Globe Valves – under evaluation.
Manual Butterfly valves & NRVs– price bid opened.
Flanges – price bid opened.
Pipes – evaluation under progress. |