Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : NUMALIGARH REFINERY LIMITED.
Project Name : POWER RECOVERY TURBINE IN PFCCU.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
293.50293.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
97.220097.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20250/07/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1560

Ministry Review Date

LatestLastPhysical Progress (%)Status
92Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks