Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : NUMALIGARH REFINERY LIMITED.
Project Name : DCU REVAMP PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    7

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3700370

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
250.1705.34255.51

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/010/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1110

Ministry Review Date

LatestLastPhysical Progress (%)Status
56.1Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone