Construction :
1. Compound wall construction- Progress achieved is 50 %. Super structure works commenced.
2. Tankage works - Schedule - 1 78 % works completed.
3. Tankage Schedule-2 - 58% Works completed.
4. Land development and TT parking area -100 % work completed.
5. PEB sheds - 31 % work progress.
6. Piling works – 100% work completed.
7. Road and Drains – 29.5 % work progress achieved.
8. Civil Building works- Cumulative progress achieved 41%.
9. PO placed for Pipeline works – 13 % cumulative progress achieved.
10. Dyke wall, pedestal works and Pit- 28 % cumulative progress achieved.
11. Electrical works – Initial datasheet and supply items details submitted for approval clearance provided for HT cable.
12. TAS works – KOM held with vendor. Initial data submission and FDS under review.
| 1. EPMC for Design engineering consultancy- PO Placed.
2. Construction of Compound wall- PO placed.
3. Procurement of steel plates- Tender floated, TE completed.
4. Study for QRA, ERDMP & HAZOP: PO placed.
5. Topographical Survey works: PO placed.
6. Tankage works Tender floated. Technical evaluation completed. PO placement under progress
7. PEB sheds - Tender floated, TE in progress.
8. Land development - Tender floated TE in progress.
9. Piling works - Tender floated with due date 8th April 2024. |