POs for piping, valves, Flanges Fasteners etc. have been placed. Major Piping Materials has been received on
site. Supply order given for DCS. Other critical items like Gas metering, Ball Valves, Pumps and other items are
under advance stage of tendering.
¿
¿ TPI tender has been awarded to M/s CEIL on 30.05.2024.
Civil & Structure works awarded on 13.09.24 to M/s Ray Engineering Pvt. Ltd. Offsite pipe-rack area cleaning
and piling works in progress. Progress is 7.1 % vs 22.5%.
¿
¿ Material handling contract has been awarded to M/s Satyasai Engineering & Construction on 01.08.2024.
Building works by M/s Sharad Construction Pvt. Ltd.: Progress is 54.3 vs 91.8 %. All piles of control room are
completed and piling work of M&I building, warehouse building and pipe rack are completed (1010/1010 piles ).
Raft work and wall work of blast proof control room building is completed. Slab work completed. 5378/9125 M3 of
RCC completed. Dismantling of old MM building has been completed and Piling of M&I building is completed.
Piling work under progress at Product terminal building (142/142 completed). Office building: RCC for foundation
& column of Office building is completed. Slab casting done on 30.04.25. Brick work under progress.Repeater
building works in progress at Abhva SV station, Bhata SV station, Umbhrat (old) and Kribhco Terminal is in
progress. | * NOA was placed on 31.07.2023 to M/s. Engineers India Limited (EIL), Delhi to execute the project on EPC reimbursable basis.
* Engineering in progress. 60% 3D Model was completed on 10.01.2024 and HAZOP for the project was done on 06.12. 2023.
* Insurance NOA has been issued to M/s Oriental Insurance Company Ltd on 31.01.2024.
* All major P&IDs has been released.
* TPIA & Building work tender is in advance stage. Composite work tender and Material handling tender are under preparation. |