T&I activities:
CPAs for PLB (Leighton Eclipse), Cargo Barges (Aquafloat ,KM-180) , DSV (Wilchief-1), Towing Tugs( Titan
Energy , Ivy ) , AHTs( Shakti, AK-9) , Crew Boats(KPS-Shivali , Gomti & Mahi)) ,AWB( Urja) have been closed.
PLB- Barge-2 ( DLB Kenenna) CPA has issued for Dry tow transportation from Nigeria to India. Ministry of
Defence clearances 9 /14 completed. MOHA clearances are under process.
¿
¿ Pre-Construction Survey by Acoms 11 completed( 19/19 segments).
DP-DSV -Wilchief-I mobilized on 24-10-2024 for Thickness Gauging and Cut point identification on existing
pipeline, Coating removal for SPRU Installation, Bow string installation and Temporary Support Installation.
¿
Pipe Laying Barge Leighton Eclipse was expected to be mobilized on 28-10-2024 but delayed due to
malfuntioning of tow Tug.
¿
¿ LOIs issued for Automatic welding, NDT.
¿ Pipe Laying Barge: - PLB Leighton Eclipse reached Heera Field on 27.11.2024 to initiate Pipe Lay.
¿ Pipe lay started on 04.12.2024
Laying of 14 (HSC-HRG, HSD-HRC, HE-HRG, HRG-HS,HRG-HX, WI2-N3 ,SA-SB, SF-BHS, SQ-BHS & RS8-
ID, NM-MNP, IU-ICG, SE-MSP & SJ-SA) out of 19 segments completed on 29.04.2025.
¿
HSC-HRG, HSD-HRC, HE-HRG, HRG-HS,HRG-HX, SA-SB, WI2-N3, SF-BHS, RS8-ID, SQ-BHS & NM-MNP -
11 segments handed over to Asset.
¿
Pipe laying progress was slow due to T&I contrcators reported commercial issues and Technical issues of
Eclipse.
¿ All the vessels have been demobilised from Offshore | * Project awarded to M/s Mazagon Dock Shipbuilders Ltd. on 07.12.2023
* Kick off meeting held on 15.12.2023 with M/s MDL. 1st MRM held on 09.01.2024.
* M/s Fugro mobilised the vessel on 14th Jan 2024. Pre-Engineering Survey completed on 30th Jan 2024 for all the segments.
* Design Engineering by M/s Oceanergy is in progress.
* All 9 PO placed including T&I contractor & PMC, Design & Survey agencies , LSAW & Seamless linepipes, Coating agency, flanges, SPRU. PO is being placed for insurance. PO placed to WERL: T&I and PMC agency
¿ Draft Planning package submitted.
¿ Cutting of billets started on 27.03.2024.
|