Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HPOIL Gas Pvt. Ltd.
Project Name : HPOIL GAS PVT LTD.

Reported Date : 07-MAY-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3340334

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
.850.08.93

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20250/05/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
76.110

Ministry Review Date

LatestLastPhysical Progress (%)Status
83.05Completed

Monthly Status

Background Information

• Total 26 CNG stations are commissioned on date. Daily average sales improved from 25000 Kgs/Day to 32000 KGs/day. Gas sourcing is from CGS, Mauje Vadgaon, Kolhapur • Type-3 mobile Cascades deployed to reduce cost of long-distance transportation by 40%. • Out of 26 CNG Station,7 stations are converted to online station. • Till 30.04.2024, 38352 Nos of PNG Registration 25827 Nos LMC work has been Completed. • LMC Work Riser testing work for PNG connection in progress. DRS of Kolhapur city Ichalkaranji city have been commissioned domestic PNG supply has been started in both cities. DRS of 3 Industrial areas viz. MIDC Shiroli, MIDC Gokul Shirgaon MIDC Kagal have been commissioned• Till 30.04.2024, 1096.06 Inch-KM MDPE pipeline and 656.55 inch km steel pipeline laid.• Sales started from 26 Nos of CNG stations (M/s Devgiri , M/s Gaikwad, M/s Disha , M/s HP Highway, M/s Sudarshan, M/s Mangave, M/s Deepraj, M/s Londhe, M/s Kondusker M/s India Auto, M/s Beharji Petrolium, M/s Vakratunda Petrolium, M/s Laxmi Malkapur, M/s Hajare Petrolium, M/s Sushant Transport, M/s Tare, M/s Umiya, M/s Kesarkar M/s Deokar,M/s JB Petrolinks, M/s Kagal MS, M/s Panchaganga, M/s Warna, M/s Madnaik Fuels Services, M/s Balaji Petroleum, M/s N.S. Petroleum ). • CGS, Mauje Vadgaon, Kolhapur commisioned on 7th February 2022 • DCU,Kolhapur City is commisioned on 24.02.2022 and PNG domestic started in Kolhapur City.• Successfully Commissioned 53.95 Km length of MDPE Network in Kagal Five Star MIDC thru DRS and started PNG supply to customer. • Commissioning of Online 28Km of MDPE Network in Industrial Area MIDC Shiroli having 480 Nos of industrial potential. • Successfully Commissioned DCU and 7.4 Km length of MDPE Network in Kolhapur City and started supply to PNG Customer.•Total 7 Nos of online DRS are commissioned in Kolhapur GA (At Kagal, Shiroli, Kolhapur City, Golkul Shirgaon, Ichalkaranji) •Commisioned steel pipeline network from Panvhganga River to Kolhapur City •07 Commercial customers and 22 industrial cusotmers commissioned• Till 30.04.2024, 5467 Nos of domestic customer are converted. Total 250.65 km MDPE pipeline and 70 km Steel pipeline is commisioned till date.• Total 23 CNG stations are commissioned on date. Daily average sales improved from 25000 Kgs/Day to 32000 KGs/day. Gas sourcing is from CGS, Mauje Vadgaon, Kolhapur • Type-3 mobile Cascades deployed to reduce cost of long-distance transportation by 40%. • Out of 23 CNG Station,7 stations are converted to online station. • Till 31.03.2024, 37598 Nos of PNG Registration 25231 Nos LMC work has been Completed. • LMC Work Riser testing work for PNG connection in progress. DRS of Kolhapur city Ichalkaranji city have been commissioned domestic PNG supply has been started in both cities. DRS of 3 Industrial areas viz. MIDC Shiroli, MIDC Gokul Shirgaon MIDC Kagal have been commissioned• Till 31.03.2024, 1081.44 Inch-KM MDPE pipeline and 653.56 inch km steel pipeline laid. • Sales started from 23 Nos of CNG stations (M/s Devgiri , M/s Gaikwad, M/s Disha , M/s HP Highway, M/s Sudarshan, M/s Mangave, M/s Deepraj, M/s Londhe, M/s Kondusker M/s India Auto, M/s Beharji Petrolium, M/s Vakratunda Petrolium, M/s Laxmi Malkapur, M/s Hajare Petrolium, M/s Sushant Transport, M/s Tare, M/s Umiya, M/s Kesarkar M/s Deokar,M/s JB Petrolinks, M/s Kagal MS, M/s Panchaganga, M/s Warna ). • CGS, Mauje Vadgaon, Kolhapur commisioned on 7th February 2022 • DCU,Kolhapur City is commisioned on 24.02.2022 and PNG domestic started in Kolhapur City.• Successfully Commissioned 53.95 Km length of MDPE Network in Kagal Five Star MIDC thru DRS and started PNG supply to customer. • Commissioning of Online 28Km of MDPE Network in Industrial Area MIDC Shiroli having 480 Nos of industrial potential. • Successfully Commissioned DCU and 7.4 Km length of MDPE Network in Kolhapur City and started supply to PNG Customer.•Total 7 Nos of online DRS are commissioned in Kolhapur GA (At Kagal, Shiroli, Kolhapur City, Golkul Shirgaon, Ichalkaranji) •Commisioned steel pipeline network from Panvhganga River to Kolhapur City •07 Commercial customers and 22 industrial cusotmers commissioned• Till 31.03.2024, 5409 Nos of domestic customer are converted. Total 213 km MDPE pipeline and 70 km Steel pipeline is commisioned till date.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks