Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : POL AND LOBS INSTALLATIONS WITH RECEIPT PIPELINES AT RASAYANI.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
258502585

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
402.8335.7224.57463.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20260/05/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
53.8Ongoing

Monthly Status

Background Information

1)Status of Rasayani BOT- CTE , PESO Initial approval received Steel plates for Tankage work received.53.8% physical progress acheived. Land development works in progress. Tankage works and civil buildings in progress 2)Status of Rasayani POL- CTE received .Contour survey & soil investigation completed. Steel plates for Tankage work received. Tankage works and civil buildings works in progress. Land development, PCVO crew room and boundary wall works in progress. Siding works in progress.53.8% Physical progress achieved. 3)Status of Pipelines - Contracts awarded for: Offshore Pipeline laying works Battery Chargers and Battery banks CI dosing Package Ball valves Passenger Lift HDD works started in Mangroves area

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone