Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
1)Status of Rasayani BOT-
CTE , PESO Initial approval received
Steel plates for Tankage work received.53.8% physical progress acheived. Land development works in progress. Tankage works and civil buildings in progress
2)Status of Rasayani POL-
CTE received .Contour survey & soil investigation completed. Steel plates for Tankage work received. Tankage works and civil buildings works in progress. Land development, PCVO crew room and boundary wall works in progress. Siding works in progress.53.8% Physical progress achieved. 3)Status of Pipelines -
Contracts awarded for:
Offshore Pipeline laying works
Battery Chargers and Battery banks
CI dosing Package
Ball valves
Passenger Lift
HDD works started in Mangroves area
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |