Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
1)CGS Station:- Land acquired from NFL for Hook up facility, Hook agreement with GAIL signed. Tender for the CGS composite works awarded & work is in progress.
2)CNG: 32 CNG station mechanically commissioned and 26 No. CNG Station have started nozzle sales. 6 no New CNG station civil works in progress.
3)PNG: 9017 Nos LMC infra installed in HH of Sri Ganganagar/Abohar/Hanumangarh cities and 31958 no customer registration donee, 2 Nos. tender for 70000 LMC connection is awarded and work is in progress.
4)MDPE:MDPE laying permission obtained for 525 km in Sri Ganganagar and Hanumangarh. Tender for MDPE laying works in 3 cities awarded and vendors mobilization is in progress.
5)STEEL Pipeline:- Steel pipeline procurement done for 150 KM , Tender awarded for 68+140 KM steel pipeline laying works. Steel pipeline 12' & 10' lowering done for 1019.58 Inchkm.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |