Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CGD PROJECTS AT THE NILGIRIS AND ERODE DISTRICTS.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
368503685

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
188.764.6611.72205.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20300/03/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
10.8Ongoing

Monthly Status

Background Information

As of 31.05.2025,60 CNG Stations have been Mechanically completed. Out of these, 26 CNG Stations have been commissioned. Additionally,18,882 PNG Connections have been installed, and 1,316 inch-km of steel pipeline have been laid.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone