Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CITY GAS DISTRIBUTION PROJECTS AT DARBHANGA, MADHUBANI, SUPAUL, SITAMARHI AND SHEOHAR DISTRICTS.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
363803638

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
356.2824.899.17390.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20300/03/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
20.8Ongoing

Monthly Status

Background Information

As of 30.06.2025,27 CNG Stations have been Mechanically completed. Out of these, 15 CNG Stations have been commissioned. Additionally, 39,981 PNG Connections have been installed, and 2,895 inch-km of steel pipeline have been laid.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks