Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : MHN TCPP PGC BGC PROJECT (MTPBP).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2329.4502354.23

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
500.5522.45149672

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20260/05/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
478.410

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUN-2545.9Ongoing

Monthly Status

Background Information

The MTPBP project located in the Western Offshore involves the installation of a new PGC train at TCPP, addition of a low pressure stage in two existing PGCs, and modification of existing PGCs to suit the low pressure profile. The scope also includes installation of one dedicated separator, one hydrocyclone, and two condensate pumps at TCPP. Deck extension and modifications are being carried out at TCPP and TPP platforms. At MNP, a new BGC and PGC unit are being installed along with fire water system modifications and structural strengthening at MNW and MNP platforms. The project is being executed on EPC basis with NOA issued to L and T on 29 February 2024 and contract signed on 26 March 2024. As of June 2025, physical progress is 45.9 percent against the scheduled 39.2 percent. Construction and manufacturing activities are ahead of schedule. PGC and BGC units have been ordered and most long lead items including hydrocyclones, condensate pumps, HP separators, air cooled heat exchangers, and DCS systems have been ordered. Pre-engineering surveys have been completed and four MRMs have been held. Fabrication of topside modules is in progress with first steel cut carried out in November 2024. Several factory acceptance tests including those for TCPP GT and PGC packages have been completed. TCPP platform topside modification works for the 2024-25 season were completed in May 2025. Major equipment such as the TCPP PGC-C and the MHN turbine have been delivered to site. Project is progressing on schedule with completion targeted in May 2026 and no delays anticipated

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks