Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CGD PROJECT AT JAMMU DISTRICTS.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5380538

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3.87.2204.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20329/20349/2034

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
.6Ongoing

Monthly Status

Background Information

"Cumulative Achievement: CNG (No.) - 3 Steel (Inch Km) - 0 D - PNG (No.)- 0 Extension received from PNGRB due to non - availability of pipeline connectivity in the vicinity of the GA. Original Completion date is extended by PNGRB."

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks