Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : PIPELINE NETWORK PROJECT RUDRASAGAR.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
344.990344.99

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
169.86.092.09172.04

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20260/04/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
320

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-2545.3Ongoing

Monthly Status

Background Information

DCI: 115/321 submitted, Approved-61, Commented-43, Under review: 11 LOI of Seamless pipe placed on M/s MSL and LOI of ERW pipe placed to M/s Rantnamani & M/s Welspun. LOI of MIJ, Flow tee, Launcher / Receiver, HT cable, UPS & Hot Induction bend placed. ¿ ¿ Total pipeline 374.58 km out of 377.84 km arrived. (99.13%). Complete Qty of heat shrink sleeve arrived at site. Dismantling of existing structure at RDS-IV completed as marked for Manifold & Launcher/ Receiver. EQT test done. ¿ WQT of 6 no.s done. Earth filling work at RDS-GGS-IV & III in progress Pipeline Laying Progress: Sch./Act 6468%/9.99%. The Panchnama & ROU Marking has started and 36.8 KM have been completed (Total segment-119 nos. & length- 121.51 km) and balance is in progress. ¿ Dismantling of existing structure at RDS-IV completed as marked for Manifold & Launcher/ Receiver. ¿ Earth filling work at RDS-GGS-IV & III completed. 59.89 Km (69 nos. segment) ROU handed over, welding done-42.69 km, Lowering done-34.19 Km and Backfilling-32.11 Km

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone