DCI: 115/321 submitted, Approved-61, Commented-43, Under review: 11
LOI of Seamless pipe placed on M/s MSL and LOI of ERW pipe placed to M/s Rantnamani & M/s Welspun. LOI
of MIJ, Flow tee, Launcher / Receiver, HT cable, UPS & Hot Induction bend placed.
¿
¿ Total pipeline 374.58 km out of 377.84 km arrived. (99.13%). Complete Qty of heat shrink sleeve arrived at site.
Dismantling of existing structure at RDS-IV completed as marked for Manifold & Launcher/ Receiver. EQT test
done.
¿ WQT of 6 no.s done. Earth filling work at RDS-GGS-IV & III in progress
Pipeline Laying Progress: Sch./Act 6468%/9.99%.
The Panchnama & ROU Marking has started and 36.8 KM have been completed (Total segment-119 nos. &
length- 121.51 km) and balance is in progress.
¿ Dismantling of existing structure at RDS-IV completed as marked for Manifold & Launcher/ Receiver.
¿ Earth filling work at RDS-GGS-IV & III completed.
59.89 Km (69 nos. segment) ROU handed over, welding done-42.69 km, Lowering done-34.19 Km and
Backfilling-32.11 Km | |