> Civil works for TTPA - Completed
> Civil works for Boundary Wall - Boundary wall under completion (150 RM) & Overhead water tank Installation in progress.
> Mechanical Package-I (New MS / Fire Water Tanks, FWPH & allied piping works)- LOA placed on 30.09.2024. Site handed over on 07.11.2024.Due to slow progress and failure to perform as per contractual stipulation, Contract is terminated on 16.04.2025.
> Civil Package-1(Non Plant Buildings, Road, Drain, Cable Bridge etc.)- LOA placed on 24.10.202.
>> Control room/ PMCC: Plinth beam work completed, super structure work in progress.
>> Drivers rest & FAN room: Work completed up-to plinth beam level, super structure work in progress.
>> Storeroom: Work completed up-to plinth beam level, super structure work in progress. | |