Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : AUGMENTATION OF DIMAPUR DEPOT, DIMAPUR.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
227.620227.62

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4.1.441.586.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20270/011/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250

Ministry Review Date

LatestLastPhysical Progress (%)Status
18Ongoing

Monthly Status

Background Information

> Civil works for TTPA - Completed > Civil works for Boundary Wall - Boundary wall under completion (150 RM) & Overhead water tank Installation in progress. > Mechanical Package-I (New MS / Fire Water Tanks, FWPH & allied piping works)- LOA placed on 30.09.2024. Site handed over on 07.11.2024.Due to slow progress and failure to perform as per contractual stipulation, Contract is terminated on 16.04.2025. > Civil Package-1(Non Plant Buildings, Road, Drain, Cable Bridge etc.)- LOA placed on 24.10.202. >> Control room/ PMCC: Plinth beam work completed, super structure work in progress. >> Drivers rest & FAN room: Work completed up-to plinth beam level, super structure work in progress. >> Storeroom: Work completed up-to plinth beam level, super structure work in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone