Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : SETTING UP POLYPROPYLENE UNIT AT KOCHI REFINERY.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
446004460

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
126.497.117.2240.7

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20270/010/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
11.1Ongoing

Monthly Status

Background Information

1)Wall Construction along the boundary in progress. 100% completed. 2)Rock Blasting activities Completed- 22,000 m3 completed out of estimated 22,000 m3 3)Geotechnical Investigation works completed. 4)Site Grading activities completed. 5)Site Enabling Works- 70.5% completed against construction scheduled 83.8%. Construction of RCC/Bitumen Road, Retaining wall in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks