Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
1)Wall Construction along the boundary in progress. 100% completed.
2)Rock Blasting activities Completed- 22,000 m3 completed out of estimated 22,000 m3
3)Site Grading activities completed.
4)Construction Power Tender- 14 out of 16 foundation casting completed for High mast, LT Cable received at site.HT Cable despatched.
5)Overall Physical progress reaching 10.1% against the planned 12.4%.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |