Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : SETTING UP POLYPROPYLENE UNIT AT KOCHI REFINERY.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
446004460

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
126.4889.1223.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20270/010/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
10.1Ongoing

Monthly Status

Background Information

1)Wall Construction along the boundary in progress. 100% completed. 2)Rock Blasting activities Completed- 22,000 m3 completed out of estimated 22,000 m3 3)Site Grading activities completed. 4)Construction Power Tender- 14 out of 16 foundation casting completed for High mast, LT Cable received at site.HT Cable despatched. 5)Overall Physical progress reaching 10.1% against the planned 12.4%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone