Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : GURDASPUR JAMMU PIPELINE.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 10 / 3 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
521.92521.92521.92

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
120.712.619.9153.2

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20267/20267/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1950

Ministry Review Date

LatestLastPhysical Progress (%)Status
35.5Ongoing

Monthly Status

Background Information

• Laying tender of the UT J&K : Contract awarded on 09.09.2024. Welding: 58.2 Km & Lowering: 50.9 Km completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks