Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : BORHOLLA GGS LIFE EXTENSION PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
198.70198.7

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
99.5.02099.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20260/05/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
26.220

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-2523.8Ongoing

Monthly Status

Background Information

OA released by SOPAN: Separator- M/s OGSP, Vessels- M/s Meenakshi Associates, P-400, Fire water pumpM/s Wilo IDBH-OGSP Cutter, HT- OGSP Cutter, FGC unit-Grand Prix, I/A Compressor-Elgi Equipment, Flare Package-Earthcon(Samia), Gas Compressor-Siemens, GDU-Indcon Pvt Ltd, Pumps-Clyde pump, I/U Compressor-Elgi equipment, Screw pump-Allweiller, PLC and DCS- Honeywell, IOPS-Carlsburg, MCC/APFC Panel-Snider. ¿ Construction Progress : Sch/Act 46.00%/11.59% PRM held at Pune LSTK office on 09.04.2025 a. HAZOP/HAZID/SIL study is held from 2nd to 4th January 2025 at Pune. Report submitted which is under review. b. Major construction activity: construction work for Boundary Wall brick work & plaster 75% complete.. Inmfocom room work upto roof beam. Road work-soil filling & compaction- 210 mtrs done ¿ ¿ Road construction work and Boundary wall construction work started.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone