OA released by SOPAN: Separator- M/s OGSP, Vessels- M/s Meenakshi Associates, P-400, Fire water pumpM/s Wilo IDBH-OGSP Cutter, HT- OGSP Cutter, FGC unit-Grand Prix, I/A Compressor-Elgi Equipment, Flare
Package-Earthcon(Samia), Gas Compressor-Siemens, GDU-Indcon Pvt Ltd, Pumps-Clyde pump, I/U
Compressor-Elgi equipment, Screw pump-Allweiller, PLC and DCS- Honeywell, IOPS-Carlsburg, MCC/APFC
Panel-Snider.
¿
Construction Progress : Sch/Act 46.00%/11.59% PRM held at Pune LSTK office on 09.04.2025 a.
HAZOP/HAZID/SIL study is held from 2nd to 4th January 2025 at Pune. Report submitted which is under review.
b. Major construction activity: construction work for Boundary Wall brick work & plaster 75% complete..
Inmfocom room work upto roof beam. Road work-soil filling & compaction- 210 mtrs done
¿
¿ Road construction work and Boundary wall construction work started. | |