Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-3
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
259.58 | 213.82 | 889.22 | 1362.62 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Procurement:
¿ Rolling of 12" & 14 " line pipes Completed.
¿ 3LPP Coating of 12" Line Pipes completed and 3LPP Coating of 14" line in Progress.
¿ MTOs/MRs released for piping, valves, Structural material for Topside works.LPP
Fabrication Works
¿ MFF Hazira: Riser clamp fabrication is in progress.Topside Fabrication for MUT Scope completed.
¿ Seamless Pipes: 100% Rolling of Seamless line Pipes for PRP VIII Gr-B & MUT alternate line scope completed.
¿ Mathews Yard: Fabrication Work for topside of MNP & NQP completed.
¿ At JSW yard:
¿ 24" LSAW Pipes: LSAW pipe rolling completed.
¿ 3LPP Coating of 62 Km ( approx.) Completed.
¿ CWC Coating of 48 Km line pipes Completed.
¿ Anode installation in Progress | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |