Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : HP TRIJET UNIT IN VR.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 5 / 5 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1930193

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
.380.05.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20270/07/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500

Ministry Review Date

LatestLastPhysical Progress (%)Status
23Ongoing

Monthly Status

Background Information

EPCC Contract: PR with 2 stage tendering released. 1st stage tender (PQC) refloated and PQC evaluation completed. 2nd stage tender floated. Price bids opened. Quoted price of L1 vendor is very high compared to company estimate. Negotiations with the L1 bidder have been concluded and further action is under review

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks