Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
a)The project could not be taken forward due to projected higher costs of PSA unit and non finalisation of feed treatment unit/package.
b)The experiments on feed preparation unit proposed by EIL/IIP could be completed by them on 21.02.2025.
c)Based on the positive results, concluded to go with EIL-CSIR-IIP feed preparation unit technology.
d)Based on the finalisation of feed preparation package as well as PSA issues, cost estimation confirmation was received from EIL on 24.03.2025.
e)Based on this, clearance was given to EIL to proceed further with procurement activities.
f)M/s EIL furnished catch up plan.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |