Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : INTEGRATED DEVELOPMENT OF 4 CONTRACT AREAS UNDER DSF2.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6183.7906183.79

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0000

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20270/04/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
9520

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-2512.6Ongoing

Monthly Status

Background Information

Two topsides Decks fabrication at MDL yard - awarded to M/s. Carlton Industrial Engineers on 16.04.2025. Fabrication of Temporary stools and supports are in progress. ¿ Tender for 4 nos. Jacket & Decks published on 04.02.25. Technical Bid opened on 18.03.25. Price bids for 5 technically qualified Bidders opened on 13.05.2025. Price negotiation is in progress. ¿ Procurement of pipelines awarded to M/s. Jindal SAW Ltd on 07.02.25, rolling of 8" pipes completed. Rolling of 10" pipeline Segment are in progress. ¿ ¿ Order Placed by MDL for 18 of 26 LongLead items & Services. Tendering in process for LongLead items - Ball Valves (DSS & SDSS), Shutdown Valves, Two phase In-line seperators, Air compressors, MPFM, sub-sea Ball valves, & Alternate Power systems.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks