Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : CONSTRUCTION OF AVIATION FUEL FARM FACILITIES AT BHOGAPURAM AIRPORT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 16 / 14 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2400240

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
10.016.732.5819.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20260/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
87.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
35.3Ongoing

Monthly Status

Background Information

Tankage Works: Foundation works completed for ATF Tank 1,2 ,3. & water tank WT01 & WT02 . Shell course, Roof Structure and roof plate erection in progress. Overall Physical Progress- 49.67% completed. Shed Works : Foundation work completed for TT Gantry, Fire & Product Pump House, Compressor shed, TT Checking platform. Foundation Work in progress for Car and 2 wheeler parking sheds. Pumps Foundation & flooring Completed in Fire & Product Pump House. TT Gantry primary & secondary structure Erection completed for all 7 bays. Overall Physical Progress-52.13. % completed. Civil Building Works : Cable trench Foundation works in progress for MCC Building. Roof Slab RCC work in progress for TT Crew Rest Room Physical Progress. Ground floor roof slab RCC completed for Admin building cum SCADA Room. Overall Physical Progress-42.38 % completed. Compound Wall :Substructure Foundation Work completed. Columns above Plinth Level completed. 85 % Brickwork completed, Overall Physical Progress-80.45 %. Roads and Drains: Foundation Work for Tank Dyke wall in Progress, TT parking area WMM filling and compaction completed. Bunded area development in progress. Road work- area levelling, compaction and murrum filling in progress for RCC Roads. Overall Physical Progreass - 21.51%. Pipeline Works: Foundation work for Pipeline Pedastals in Progress near Bunded tank area and ATF tank area. Pipeline Sleepers construction in progress in Pump manifold area. Overall Physical Progress - 4.95 %. Electrical Works: Vendor Engineering in progress. Automation Work: Vendor Engineering in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone