Tankage Works: Foundation works completed for ATF Tank 1,2 ,3. & water tank WT01 & WT02 . Shell course, Roof Structure and roof plate erection in progress. Overall Physical Progress- 49.67% completed.
Shed Works : Foundation work completed for TT Gantry, Fire & Product Pump House, Compressor shed, TT Checking platform. Foundation Work in progress for Car and 2 wheeler parking sheds. Pumps Foundation & flooring Completed in Fire & Product Pump House. TT Gantry primary & secondary structure Erection completed for all 7 bays. Overall Physical Progress-52.13. % completed.
Civil Building Works : Cable trench Foundation works in progress for MCC Building. Roof Slab RCC work in progress for TT Crew Rest Room Physical Progress. Ground floor roof slab RCC completed for Admin building cum SCADA Room. Overall Physical Progress-42.38 % completed.
Compound Wall :Substructure Foundation Work completed. Columns above Plinth Level completed. 85 %
Brickwork completed, Overall Physical Progress-80.45 %.
Roads and Drains: Foundation Work for Tank Dyke wall in Progress, TT parking area WMM filling and
compaction completed. Bunded area development in progress. Road work- area levelling, compaction and murrum filling in progress for RCC Roads. Overall Physical Progreass - 21.51%.
Pipeline Works: Foundation work for Pipeline Pedastals in Progress near Bunded tank area and ATF tank area.
Pipeline Sleepers construction in progress in Pump manifold area. Overall Physical Progress - 4.95 %.
Electrical Works: Vendor Engineering in progress.
Automation Work: Vendor Engineering in progress. | |