Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : CONSTRUCTION OF AVIATION FUEL FARM FACILITIES AT BHOGAPURAM AIRPORT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 16 / 14 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2400240

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
10.019.313.0222.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20260/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
87.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
42.8Ongoing

Monthly Status

Background Information

Statutory Approvals PESO approval received on 25 February 2025. Labour license approved on 30 November 2024. DM NOC received on 7 March 2025. Provisional fire NOC received on 11 February 2025. APPCB CFE application submitted on 24 January 2025 and is pending. Factories initial approval received on 19 March 2025. Building permission received on 5 May 2025. AAI NOC received on 18 March 2025. Project Summary PMC order placed and team mobilized. Engineering and layout finalised and approved. All major purchase orders issued for materials, equipment, and civil works. Most key items like pipes, steel plates, pumps, transformer, and bunded tanks have been received. Tendering is complete. Construction Progress Tankage work is 63 percent complete with civil works done and mechanical works ongoing. Shed works are 83 point eight percent complete with PEB structure erection in progress. Civil buildings are 70 point two percent complete with major structures under construction. Compound wall is 92 percent complete with final items pending. Road and drain work is at 23 point five percent with foundations and filling ongoing. Hydrant pipeline work is at 7 percent with pedestals and trench work in progress. Electrical and automation item approvals and ordering are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks