Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : VISAKHA RAIPUR PIPELINE PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 22 / 21 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
221202212

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2.18.231.914.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20270/09/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
416.250

Ministry Review Date

LatestLastPhysical Progress (%)Status
4.73Ongoing

Monthly Status

Background Information

PMC EPMC contract awarded to Engineers India Limited on 29 November 2024. Ordering Orders placed for EIA and RA studies on 29 November 2024 and for VRPL land acquisition and topographic survey on 28 March 2025. Manufacturing and Delivery Not yet started. Engineering Basic engineering completed detailed engineering in progress. Layouts for Vizag DT, IPPS 2, Kantabanji depot, and indicative layouts for SV, IP, and IPPS submitted. P and IDs submitted and reviewed. MRs under review. SOQ and SCC received. Tendering Pipeline laying tender floated, bid due on 2 June 2025. Pump and scraper barrel tenders under finalization. Construction Not yet started. Commissioning and Handover Not applicable. CA Appointment and ROU AP 164 km: CA appointed, gazette issued, 3 1 notices served for 114 km, joint survey done for 106.118 km. Odisha 280 km: CA nomination received on 8 May 2025, gazette request sent. Chhattisgarh 96 km: CA appointed, draft 3 1 sent on 22 April 2025. Permanent Land for Stations IPPS1 Rayagada: Private land 4.91 acres – DCAC application filed, consent signed. Govt land 6 acres – Alienation via IIDCO, BDO approval on 27 May, topo survey on 26 May, legal docs submitted. IPPS2 Kantabanji: Private land 40.84 acres – Application submitted, 199 co-owner consents received. Govt land 2.5 acres – Alienation process underway, survey and Form 1A completed, road NOC obtained. Crossings Out of 985 crossings, demand note received for 372, NOC received for 175. SV stations 12 out of 15 land consents taken. IPS land 1 out of 2 consents taken.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <