EPMC Contract for pipeline and allied facilities awarded to Engineers India limited on 29.11.2024. Order placed for EIA & RA studies on 29.11.2024. Order placed for VRPL land acquisition and topographic survey on 28.03.2025.
Engineering :
Basic engineering completed and Schematics finalized based on hydraulics.
Layout plans for IPPS-1 & Kantabanji submitted. Indicative plot plan for Vizag-DT submitted.
SV/IP typical layout made.
P&ID’s completed. Raipur and Kantabanji terminal -under review.
HAZOP completed for pipeline portion. HAZOP for terminal portion to be scheduled.
MRs for Mainline Pumps, Booster Pumps, basket filters, Scraper traps, mainline ball valves, Check Valves submitted by EIL.
SOQ and SCC received for site enabling tender and pipeline laying tender.
Architectural drawings submitted for review.
Piling Tender draft copy submitted. Under Review.
Line Pipe tender unpriced bid opened on 06.06.25. TBE under progress. Tender floated for Mainline Pump .
Tenders of Pipeline Laying, Booster Pump, Scrapper Barrel, Basket Filter, Surge Relief Valve, Check Valves, Site Enabling and Piling tender are under finalization
AP 164 km: CA appointed, gazette issued, 3 1 notices served 9759 out of 10065, joint survey done for 137 km. Odisha 280 km: CA nomination received on 8 May 2025, gazette request sent. Chhattisgarh 96 km: CA appointed, 3 1 published on 24.06.25, notice serving in progress.
Permanent Land for Stations
IPPS1 Rayagada: Private land 4.91 acres – DCAC application filed, consent signed. Govt land 6 acres – Alienation via IIDCO, BDO approval on 27 May, topo survey on 26 May, legal docs submitted.
IPPS2 Kantabanji: Private land 40.84 acres – Application submitted, 199 co-owner consents received. Govt land 2.5 acres – Alienation process underway, survey and Form 1A completed, road NOC obtained. ROR updation in progress.
Crossings
Out of the 985 crossings, Demand note received for 485 crossings. NOC received for 252 crossing.
SV stations
13 out of 15 land consents taken and application sent.
IPS land 1 out of 2 consents taken.
| |