PMC
EPMC contract awarded to Engineers India Limited on 29 November 2024.
Ordering
Orders placed for EIA and RA studies on 29 November 2024 and for VRPL land acquisition and topographic survey on 28 March 2025.
Manufacturing and Delivery
Not yet started.
Engineering
Basic engineering completed detailed engineering in progress. Layouts for Vizag DT, IPPS 2, Kantabanji depot, and indicative layouts for SV, IP, and IPPS submitted. P and IDs submitted and reviewed. MRs under review. SOQ and SCC received.
Tendering
Pipeline laying tender floated, bid due on 2 June 2025. Pump and scraper barrel tenders under finalization.
Construction
Not yet started.
Commissioning and Handover
Not applicable.
CA Appointment and ROU
AP 164 km: CA appointed, gazette issued, 3 1 notices served for 114 km, joint survey done for 106.118 km. Odisha 280 km: CA nomination received on 8 May 2025, gazette request sent. Chhattisgarh 96 km: CA appointed, draft 3 1 sent on 22 April 2025.
Permanent Land for Stations
IPPS1 Rayagada: Private land 4.91 acres – DCAC application filed, consent signed. Govt land 6 acres – Alienation via IIDCO, BDO approval on 27 May, topo survey on 26 May, legal docs submitted.
IPPS2 Kantabanji: Private land 40.84 acres – Application submitted, 199 co-owner consents received. Govt land 2.5 acres – Alienation process underway, survey and Form 1A completed, road NOC obtained.
Crossings
Out of 985 crossings, demand note received for 372, NOC received for 175.
SV stations
12 out of 15 land consents taken.
IPS land 1 out of 2 consents taken. | |