Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : LUBE MODERNIZATION AND BOTTOM UPGRADATION PROJECT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 30 / 19 / 11

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
467904679

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
157.5714.085.76177.41

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20280/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
4.2Ongoing

Monthly Status

Background Information

1. Basic and detail engineering by PMC is in progress for EPCM facilities. 2. LSTK tender for IHCD and SDA published in NIC portal on 05.04.2025. Bid due date 31.07.2025. 3. Tender floated for site enabling activities in NIC portal on 16.06.2025. Bid due date 30.06.2025. 4. Tender floated for Tankage Works in NIC portal on 23.06.2025. Bid due date 14.07.2025. 5. Site enabling activities are in progress to handover space for units and offsite facilities inside Mumbai Refinery.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks