Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : LUBE MODERNIZATION AND BOTTOM UPGRADATION PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 30 / 19 / 11

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
467904679

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
157.576.048.04171.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20280/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
4.2Ongoing

Monthly Status

Background Information

1. MoM of EAC (Expert Appraisal Committee) meeting for grant of Environmental Clearance (EC) for LMBU project. 2. LSTK tender for IHCD & SDA published in NIC portal on 05.04.2025. Bid due date: 17.06.2025 3. Site enabling activities are in progress to handover space for units and offsite facilities inside Mumbai Refinery.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone