Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : TAPOVAN-VISHNUGAD HEP (4X130MW) (NTPC).

Reported Date : 11-MAR-11

Monthly Report : 1 / 2011

  

   

Total/Pending/Completed Milestone - 24 / 0 / 24

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2448.502448.49

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
197114802119

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20100/012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
327353

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks