Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : NATIONAL CAPITAL THERMAL POWER PROJECT STAGE-II.

Reported Date : 28-MAR-11

Monthly Report : 1 / 2011

  

   

Total/Pending/Completed Milestone - 40 / 0 / 40

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5135.3305135.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3965.1096.94062

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20100/07/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7120

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks