Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : TAPOVAN-VISHNUGAD HEP (4X130MW).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 12 / 4 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2978.48010907

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
6696.5639.53271.847007.93

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/201312/20214/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
72.4Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks