Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : FARAKKA STPP STAGE-III.

Reported Date : 14-JUN-11

Monthly Report : 4 / 2011

  

   

Total/Pending/Completed Milestone - 26 / 0 / 26

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2570.4402570.44

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
168202142445.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20100/03/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
527443

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks