Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM ASSOCIATED WITH PARBATI-III HEP.

Reported Date : 18-DEC-13

Monthly Report : 10 / 2013

  

   

Total/Pending/Completed Milestone - 11 / 0 / 11

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
557.24775.25775.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
638.67.142.69648.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20100/010/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
19.450

Ministry Review Date

LatestLastPhysical Progress (%)Status
18-JUL-07100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks