Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : NORTHERN REGION SYSTEM STRENGTHENING SCHEME-VI.

Reported Date : 11-MAY-10

Monthly Report : 3 / 2010

  

   

Total/Pending/Completed Milestone - 21 / 0 / 21

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
186.950186.95

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
98.9647.83.06149.82

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20090/03/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
35.865.01

Ministry Review Date

LatestLastPhysical Progress (%)Status
18-JUL-07100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks