Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM ASSOCIATEDWITH URI-II.

Reported Date : 22-FEB-12

MOU Status :

Monthly Report : 12 / 2011

Cost Overrun (%)-   0

Time Overrun (Months)-    7

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
238.250238.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
210.028.42.4220.82

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20115/201112/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
16.540

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-NOV-1018-JUL-07100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone