Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : KISHANGANGA HEP (3X110 MW).

Reported Date : 09-MAY-18

Monthly Report : 3 / 2018

  

   

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3642.0405882.01

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4818.99414.8967.755301.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20160/03/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
576.560

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Civil works: All the major works required for commissioning of the Project have been completed. HM Works: Completed. E&M works: • Unit-1: Commissioned on 13.03.2018. • Unit-2: Commissioned on 21.03.2018. • Unit-3: Commissioned on 30.03.2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks