Reported Date :
09-MAY-18
|
MOU Status :
Not Under MOU for 2016-2017
|
Monthly Report :
3
/
2018
|
Cost Overrun (%)- 61.5
|
Time Overrun (Months)-
26
|
Total/Pending/Completed Milestone -
6
/
0
/
6
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
4818.99 | 414.89 | 67.75 | 5301.63 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Civil works:
All the major works required for commissioning of the Project have been completed.
HM Works: Completed.
E&M works:
• Unit-1: Commissioned on 13.03.2018.
• Unit-2: Commissioned on 21.03.2018.
• Unit-3: Commissioned on 30.03.2018.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |