Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : SIMHADRI STPP STAGE -II.

Reported Date : 21-MAY-12

MOU Status :

Monthly Report : 3 / 2012

Cost Overrun (%)-   0

Time Overrun (Months)-    10

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5103.3905038.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
387852704405

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20110/03/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
0853

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed