Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : EASTERN REGION STRENGTHENING SCHEME-II.

Reported Date : 17-APR-12

Monthly Report : 2 / 2012

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
227.520227.52

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
134.15.7.9140.7

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20106/20102/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
11.640

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-NOV-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks