Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : WESTERN REGION STRENGTHENING SCHEME-V.

Reported Date : 17-JUL-19

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 5 / 2019

Cost Overrun (%)-   54.59

Time Overrun (Months)-    104

Total/Pending/Completed Milestone - 8 / 3 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
477.69738.48738.48

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
691.26.70691.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20104/20195/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5.510

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone