Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TR. SYSTEM FOR STARTUP POWER TO DVC AND MAITHON RB GEN. PROJ..

Reported Date : 28-JUL-11

MOU Status :

Monthly Report : 5 / 2011

Cost Overrun (%)-   2.96

Time Overrun (Months)-    13

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
290.490299.08

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
345.810.99346.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20100/05/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
13.720

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-JUL-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone