Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TR. SYSTEM FOR STARTUP POWER TO DVC AND MAITHON RB GEN. PROJ..

Reported Date : 08-MAR-11

MOU Status :

Monthly Report : 1 / 2011

Cost Overrun (%)-   0

Time Overrun (Months)-    1

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
340.720340.72

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
128.2831.874.22164.37

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20100/012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
79.0667.03

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-NOV-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone